Projects
Ongoing Projects
Title | Project 1 | Project 2 | Project 3 | Project 4 | Project 5 | Project 6 | Project 7 |
---|---|---|---|---|---|---|---|
Agency/Area | UZBEKGIDROENERGO, JSC Uzbekistan | Rajasthan | Maharashtra | THDC Koteshwar | Kerala | SHK Energy Storage Project by NTPC | SHK Energy Storage project by SECI |
Capacity | 50 MW | 2 MW | 999 KW | 100 KW | 25 KW | 25 MWH | 250 KWH |
Start Date | 01/04/23 | 14/03/23 | 13/06/23 | 27/04/23 | 02/06/23 | 10/10/23 | 16/10/23 |
Delivery Date | Ongoing | 20/06/23 | Material delivery started | Material delivery started | 30/08/23 | Under Execution | Under Execution |
Status | Stage 1 for 4.2 MW Under Execution | 1 Module delivered and 2 MW Under Execution | Received a letter of award on 13/06/23 and presently under execution | Received a letter of award on 27/04/23 and presently under execution | Execution is awaited as the site transfer from Irrigation Dept to EMCK is still under process | Considered world’s first Hydrokinetic Energy Storage project | Awarded by SECI |